NIT No./PR No. Business Tender Description Pre Bid Date Cost of EMD (Rs. Lakhs) Date of Advertisement Bid Submission Closing Date Tender Doc Corrigendum Status
RJ01 - PSP/SHAHPUR/ CIVIL AND HYDRO-MECHANICAL PACKAGE /002 Renewable Energy NIT for "Execution of Civil and Hydro-Mechanical Works... NIT for "Execution of Civil and Hydro-Mechanical Works on EPC - Item Rate Basis (Re-measurable) for the Scope of work defined herein, which includes Upper Approach channel, Intake pool, Upper intake structures, Upper Reservoir, Buried Penstocks/pressure shafts, vertical and horizontal Pressure Shafts along with Steel Liner, Surface Powerhouse for accommodating 5 units of 300 MW and 2 units of 150MW along with required service bay and unloading bay, Pothead yard, Tail Race Tunnels, Tailrace outlet (Lower Intake), Tail race pool , Tail Race Channel (Lower approach channel ),Lower Reservoir, PAT to service bay , Adits to pressure shafts , Hydro-Mechanical Works (including Gates, Stoplogs, hoisting arrangements, Trash Racks & valves etc. for both upper and lower intake), all other Appurtenant Works required for Commissioning of project works including Infrastructure works, Fabrication, Erection, Testing, Commissioning and conducting Performance Guarantee Testing complete and handing over in all respects of “Civil and Hydro-Mechanical Works” - 100 6th Mar'2024 5th April 2024 Click Here - Live
RJ01 - PSP/ SHAHPUR/ ELECTRO-MECHANICAL PACKAGE/001 Renewable Energy NIT for "Design, Engineering, Model Testing,... NIT for "Design, Engineering, Model Testing, Procurement, Manufacturing, Shop Testing, Packing, Insurance, Supply, Transportation to site, Storage, Installation, Erection, Testing & Commissioning, Trial Operation, and conducting Performance Guarantee Tests of Electro-Mechanical Package for 1800 MW Pumped Storage Project (PSP). - 100 6th Mar'2024 29th May'2024 Click Here - Live
RJ02-PSP/SUKHPURA/ELECTRO-MECHANICAL PACKAGE/001 Renewable Energy NIT For "Design, Engineering, Model Testing,... NIT For "Design, Engineering, Model Testing, Procurement, Manufacturing, Shop Testing, Packing, Insurance, Supply, Transportation to site, Storage, Installation, Erection, Testing & Commissioning, Trial Operation, and conducting Performance Guarantee Tests of Electro-Mechanical Equipment from Main Inlet Valve (MIV) to LV terminal connection of Generator/Motor transformer on EPC Basis on FIRM & FIXED Price till the completion of Project Schedule for 2560MW Pumped Storage Project. 01st Aug'2022 100 21st Jul'2022 30th Nov'2022 Click Here - Live
MP01-PSP/GANDHI SAGAR/CIVIL AND HYDRO-MECHANICAL PACKAGE/002 Renewable Energy NIT For "Civil and Hydro-Mechanical Works on EPC Basis,... NIT For "Civil and Hydro-Mechanical Works on EPC Basis, along with complete detailed engineering (including review of Electro-Mechanical design & drawings), Scope of work will include all components of project i.e. Upper embankment dam, bottom outlet at upper reservoir, Intake Structure, Buried Penstocks, vertical and horizontal Pressure Shaft along with Steel Liner, Surface Powerhouse, Tail Race Tunnel, Outlet structure, Tail Pool, Coffer Dam & Temporary Dike, Tail race channel (Off-shore Construction), Adits, Hydro-Mechanical Works (including Gates, Stoplogs, hoisting arrangements, Trash Racks & valves etc), all other Appurtenant Works required for completion of project, Infrastructure works along with review & interface of Electro-Mechanical Works, Fabrication, Erection, Testing, Commissioning and conducting Performance Guarantee Testing complete and handing over in all respects of “Civil and Hydro-Mechanical Works” on “EPC BASIS”, remedying of the defects if any, and other activities incidental to the completion of Works for 1440 MW Pumped Storage Project (PSP) at Khemla Block Village, Neemuch Dist., Madhya Pradesh, India 23rd Dec'2021 - 12th Dec'2021 12th Oct'2022 Click Here 02 Live
IREP/SAUNDATTI/CIVIL AND HYDRO-MECHANICAL PACKAGE/002 Renewable Energy NIT For "Execution of Civil and Hydro-Mechanical Works on EPC Basis... NIT For "Execution of Civil and Hydro-Mechanical Works on EPC Basis, along with complete detailed engineering for the project, Scope of work will include all Civil and H&M components of project i.e. Upper embankment dam, Lower embankment dam (to be included), bottom outlet at upper reservoir, Intake Structure, Intake Tunnel along with Steel Liner, Penstocks, vertical and horizontal Pressure Shaft along with Steel Liner, Surface Powerhouse, Tail Race Tunnel, Outlet structure, Tail race channel, Adits, Hydro-Mechanical Works (including Gates, Stoplogs, hoisting arrangements, Trash Racks & valves etc), all other Appurtenant Works required for completion of project, Infrastructure works along with review & interface of Electro-Mechanical Works, Fabrication, Erection, Testing, Commissioning and conducting Performance Guarantee Testing complete and handing over in all respects of "Civil and Hydro-Mechanical Works" on "EPC BASIS", remedying of the defects if any, and other activities incidental to the completion of Works for 1260 MW Pumped Storage Project 05th Apr'2021 1000 26th Mar'2021 30th May'2022 Click Here - Live
MP01-PSP/GANDHI SAGAR/ELECTRO-MECHANICAL PACKAGE/001 Renewable Energy NIT For "Design, Engineering, Model Testing, Procurement,... NIT For "Design, Engineering, Model Testing, Procurement, Manufacturing, Shop Testing, Packing, Insurance, Supply, Transportation to site, Storage, Installation, Erection, Testing & Commissioning, Trial Operation, and conducting Performance Guarantee Tests of Electro-Mechanical Equipment from Main Inlet Valve (MIV) to LV terminal connection of Generator/Motor transformer on EPC Basis on FIRM & FIXED Price till the completion of Project Schedule for 1440MW Pumped Storage Project 29th Nov'2021 - 17th Nov'2021 30th Dec'2021 Click Here - Closed
IREP/SAUNDATTI/ELECTRO - MECHANICAL PACKAGE/001 Renewable Energy NIT For "
PACKAGE-A:
Electro Mechanical Equipment's...
NIT For "
PACKAGE-A:
Electro Mechanical Equipment's from MIV to LV side of generator transformer, broadly consists of "Main Inlet Valve (MIV) and, its associated equipment, Pump-Turbine & Generator - Motor along with its Auxiliaries (2x126 MW & 4x252MW - Variable Speed Machines), Governors, AC Excitation System, associated LV and MV switchgear, Generator Circuit Breaker and Phase Reversal Isolators, current limiting reactors, isolated phase bus duct Dynamic braking/starting switch, total plant SCADA, Instrumentation, Auxiliaries, Controls and Protection, Special interconnecting Cables & accessories in complete" including supply of Critical, recommended & mandatory spares.
PACKAGE-B:
Balance of Plant (E-BoP & M-BoP): 400 kV Pothead yard equipment-CT, PT, CVT, Lightening Arrestors, Wave Traps, Isolators, OPGW, PLCC/FOTE, MV & LV Switchgear Panels, Earthing System, FRLSH Cables (Power, control & Instrumentation with accessories), Cable Trays and Accessories, Auxiliary Station Transformers, Auxiliary Unit Transformers, CT's, LAVT, Battery System, Illumination System, HVAC System, including all associated Structures and accessories in complete, including Power Transformers, 400 kV GIS, EOT Cranes, Fire Protection, Detection and Firefighting system, DG Set (11kV, 1010 kVA) etc. with integration of system to plant SCADA for 1260 MW Pumped Storage Project
28th Feb'2020 1500 13th Feb'2020 31st Jan'2022 Revised Parameters Issued - Closed
AP01 IREP/PINNAPURAM/ASSS/005 Renewable Energy NIT For "
PACKAGE-A:
Electro Mechanical Equipment's...
NIT For "Construction of the Asphalt Surface Sealing System (ASSS) on rockfill Dams (AFRD), TRC and in Intake Areas (as shown on the corresponding drawings)/ includes placing and compaction of 2B filters, application of the prime and tack coat, placing and compaction of the layers of the asphalt surface sealing system, Bituminous coat. The Asphalt Concrete Contractor (ACC) shall properly backfill Mastic Pockets, embed the Copper Water Stoppers into the asphalt and place the Glass Grid. All joints shall be properly sealed and treated. The ACC shall provide sufficient adequate men, machinery, tools & tackles, equipment, handling, testing of material to satisfy the requirements given in the technical specifications and to reach the envisaged placing rate. Transportation of asphalt from the mixing plant to the placing unit will be done by the ACC
16th Aug'2021 - 23rd Jul'2021 30th Sep'2021 Bids Recevied - Closed